Who does what: client, project lead and suppliers

You want responsibilities written down before work starts, so nothing falls between you, a project lead and the suppliers.

Opens WhatsApp with a draft you can edit before sending. Nothing is sent automatically.

The short answer

The client decides and approves. The project lead plans, coordinates and keeps decisions and actions visible. Specialist suppliers deliver their own technical and operational work. Most problems on an event start where two of these assume the other has a task.

Write the split down for every area of the event before work starts, and keep one accountable name against each line. The table below is a starting point to adapt.

The three roles in one sentence each

  • Client: owns the event, its purpose, the programme, the budget and every approval.
  • Project lead: owns the plan and the follow-through, within a written scope, without taking over decisions that belong to the client.
  • Specialist suppliers: own the delivery of their service and answer for it under their own contract.

Responsibility table

Typical split on a professional event, to adapt to your scope
AreaClientProject leadSpecialist suppliers
Purpose, audience and programmeDecides and approvesRecords decisions, flags gapsNot applicable
Speakers and contentSelects and approvesTracks invitations, briefs and deadlinesNot applicable
Budget and contractsApproves, signs and paysPrepares comparisons and keeps the budget position currentQuote, contract and invoice
Venue selectionApproves the choiceWrites requirements, compares proposals, coordinates site questionsVenue provides facilities and confirms in writing
Audio-visual, staging and streamingApproves the supplier and the briefCoordinates handovers and checks the plan against the programmeDesign, supply and operate
CateringApproves menus and numbersCoordinates dietary information and timingsPrepare and serve
Registration and delegate dataOwns the data and the policySets the process steps with the supplierOperate the registration system
Delegate and speaker communicationsApproves messagesKeeps the communications calendar and draftsSend through their systems where appointed
Sponsors and exhibitorsOwns the relationships and commitmentsKeeps a delivery checklist for what has been promisedSupply their own materials and staff
Legal, safety, accessibility and permitsObtains answers from the qualified partyLists the questions and records the answersAdvise within their own field
On-site coordinationAttends and decidesPresent as agreed in the scopeRun their own areas
Reporting and handoverReviews and confirmsPrepares reports and handover documentsProvide their closing documents

Boundaries worth stating plainly

  • A project lead does not replace a qualified adviser on legal, safety, accessibility, privacy or accreditation questions.
  • A project lead does not supply technical production. That belongs to the suppliers you appoint.
  • Sponsor and ticket sales are not part of the service. Coordinating what has been promised to sponsors is.
  • On-site presence and authority to commit money are set in the written scope, never assumed.

One accountable name per line

A line with two accountable people has none. A line with none will be found out on the day. Use the responsibility matrix builder to mark who is responsible, accountable, consulted and informed for each task, and to see lines with no owner or two.

Anonymised role labels work when names are sensitive or still undecided.

Keeping it current

Review the table at each milestone and whenever a supplier is added or a person changes role. Record changes in the decision log so the history is clear. See how an engagement works.

Worked example · Fictional example

A fictional gap in who sends reminders

Fictional organisation and figures, for illustration only.

At a fictional pharmacists' forum, the registration supplier assumes the secretariat sends payment reminders, and the secretariat assumes the supplier's system does. A week before the event, 40 delegates have registered and not paid.

The project lead finds the gap in a review of the matrix, where the line 'payment reminders' shows no owner. The client assigns it to the secretariat, the supplier supplies the list of unpaid delegates, and the matrix now names both.

Use this yourself

Responsibility matrix rows to copy

Add one row per task. Use R for responsible, A for accountable, C for consulted and I for informed. Aim for exactly one A per row.

TaskClientProject leadSupplier (name the type)Decision date
Approve the programmeAI-Date
Write the venue briefCA and R-Date
Operate the registration systemACRDate
Send payment remindersACRDate

Open the tool: Event responsibility matrix builder

Handle it in-house, or bring in help?

Your team can usually handle this when

  • Your team is small, the roles are clear and suppliers are few.
  • One person can hold the whole matrix and keep it current.
  • You have worked with the same suppliers before.

Outside planning help earns its fee when

  • Several committees or departments each assume someone else owns a task.
  • You are adding a project lead and need the boundary written down.
  • Procurement wants to see who is accountable for what.

Want the split written for your event?

If your event has overlapping owners or tasks nobody holds, a project lead can draft the responsibility matrix from your brief, mark the lines with no owner and keep it current through delivery. Send the list of areas you are unsure about.

Ask for a responsibility matrixOpens WhatsApp with a draft you can edit before sending. Nothing is sent automatically.Conference project lead

Questions organisers ask

Who is accountable if a supplier fails?

The supplier answers for its own service under its contract. The project lead coordinates the response, and the client decides on any consequences.

Can the project lead sign contracts?

Authority to commit money or sign is set in the written scope. The default is that the client approves and signs.

Does this table apply to staff events?

The structure does. For staff events, add HR and the executive sponsor as clients. See staff and internal events.

Where can I see a worked example?

The sample planning pack shows responsibility matrix rows in context. It is fictional.